Construction Update – 8/28/17 from Ryan Nebel, Construction Superintendent
  • Polish concrete in Food Pantry, Clothes Closet and all rooms.
  • Insulate all interior and exterior walls throughout building.
  • Finish brick on all elevations.
  • Hang sheetrock throughout building.
  • Mechanical/Electrical/Plumbing rough-in in attic space.