Construction Update – 7/10/17 from Ryan Nebel, Construction Superintendent Activities occurring this week at GFCFS:
  • Began to set wood trusses. Three more deliveries and two crane mobilizations remain.
  • All wood trusses will be set by next Thursday.
  • Start roof sheathing on Friday.
  • Wood framing of exterior shear walls complete.
  • Exterior sheathing installed.
  • Interior walls will be complete by next week.
  • Start air barrier and Tyvek install Friday.
  • Pouring curb and gutter on perimeter of site.
  • Light pole rough-in ongoing.
  • Temp stone site access road complete.