Construction Update – 7/17/17 from Ryan Nebel, Construction Superintendent Activities occurring this week at GFCFS:
  • Setting roof trusses this week. All roof trusses will be set by Friday.
  • Roof sheathing ongoing.
  • Interior wall framing complete.
  • Tyvek membrane wrap complete.
  • Wall reinforcement for dental accessories, equipment, and casework ongoing.
  • Polished concrete area covered with Core-Ply to protect slab finish.
  • Perimeter curb install complete – for now.
  • Light pole rough-in will be complete by Friday.
  • Framing of outdoor canopy areas ongoing.
  • Stabilization and seeding of all areas outside of curb and gutter.
  • Heavy equipment being removed from site.
  • Survey of property across the street for future force main to be completed by Friday.