- Roof sheathing is complete.
- All interior framing will be complete by middle of next week.
- Fascia board, soffit vent installation ongoing.
- Roofing underlayment starts on Friday.
- Roofing with asphalt shingles to follow.
- Mechanical, electrical, and plumbing rough-in of walls started this week.
- Brick veneer to start next week.