- Wood framing of EXTERIOR shear walls ongoing. Will be complete by next Tuesday.
- Wood framing of INTERIOR walls ongoing.
- Light pole rough-in ongoing.
- All rain leaders for downspouts have been installed.
- All curb and gutter has been laid out.
- Temp power to building has been installed and underground electrical to building is complete.