- Set all windows and seal
- Finished all interior framing and structural reinforcement
- Set brick at north, west and east elevations
- Finishing shingling of roof
- Electrical rough-in of walls throughout building
- Sanitary/Vent install throughout building
- Water line install throughout building
- Setting interior and exterior door frames
- All HVAC equipment will be delivered and setting AHU’s in attic