Construction Update – Week of 6/12/17
from Ryan Nebel, Construction Superintendent
Activities occurring this week at GFCFS:
- Concrete slab prep is ongoing.
- Concrete slab pours slated for next week.
- Brick mason finished interior shear wall foundations and pouring bond beam Thursday.
- Termite treatment done last Saturday.
- Underground Electrical rough-in ongoing inside of building.
- Vacuum lines installed and tested.
- Setting steel columns on Thursday.
- Continue to haul out dirt from site.
- Installing storm structures and storm line.
- Sediment pond stabilized.
- Activities occurring this week at GFCFS:
- Concrete slab prep is ongoing.
- Concrete slab pours slated for next week.