Construction Update – 6/26/17 from Ryan Nebel, Construction Superintendent Activities occurring this week at GFCFS:
  • Concrete slab pour completed for second half of building. (140 cubic yards poured. That’s 17 concrete trucks.) This completes concrete pour for the building.
  • Wall layout will be complete by Thursday evening.
  • Install rain leaders for future downspouts.
  • Grading entrance and grading curb and gutter.
  • Existing light pole removed at entrance.
  • Wood framing starts tomorrow. Carpenter crew and wood arrive tomorrow morning.
  • Light poles electrical rough-in starts tomorrow.
  • Continue to haul off remaining dirt spoils.