Construction Update – 6/5/17 from Ryan Nebel, Construction Superintendent Rainy day on Monday but back to work on Tuesday. Activities occurring this week at GFCFS:
  • All interior concrete footings should be poured by Friday or Saturday.
  • Brick mason will install interior shear wall foundations.
  • Termite treatment of the building pad will be on Thursday.
  • Concrete slab prep will start on Friday.
  • 2″ domestic water service was installed to the building from the 8″ mail line
  • Continue to haul out dirt from the site.