Construction Update – 11/27/17
from Ryan Nebel, Construction Superintendent
- Installed all carpet and vinyl flooring
- Installed dumpster pad
- Poured concrete aprons and loading dock area
- Set all light poles
- Moved wooden shed to final location
- Completed all HVAC enclosures
- Completed final paint throughout building
- Trimmed out electrical, mechanical, and plumbing fixtures
- Installed all window shades
- Entire site fine graded and ready for pavement