Construction Update – 10/16/17 from Ryan Nebel, Construction Superintendent
  • All flooring materials delivered
  • Started ceramic tile installation
  • Set all HVAC units
  • Turned on permanent power to building
  • Hung all doors and stared door hardware install
  • Started wood shelving in storage rooms and stockrooms
  • Installed data equipment
  • Mobilized heavy equipment for sitework
  • Finished light fixture installation in ceilings