- finished prime painting walls throughout building
- finished framing acoustical ceilings through building
- finished hanging last areas of sheet rock
- set louvers
- connecting power panelboards and pulling wire to terminals
- relocated red shed to building site
- finished cutting in sprinkler heads in ceiling
- installed mechanical grilles and diffusers throughout ceilings
- finished installing the cast stone wainscoting miter sections
- all masonry work on building is complete