Construction Update – 11/23/17
from Ryan Nebel, Construction Superintendent
- Vinyl flooring installed throughout dental area
- Installing switches and receptacles throughout building
- Spot priming and spots point up of walls
- Walls almost ready for finish paint
- Install basestone throughout parking lot
- Completed force main connections from old building and new building and tied into e existing manhole across Route 6
- Installed bathroom accessories and toilet partitions
- Testing and balancing of HVAC system
- Finished installation of slat walls in Clothes Closet
- Setting plumbing fixtures and sinks throughout building
- Mounted light sconces around exterior of building