- Dominion Power installed permanent power to building
- Completed 50% of light fixtures installation in ceilings
- Completed 75% mechanical grills and diffusers in ceilings
- Completed hardieplank siding
- Completed all exterior soffit trim
- Started install of lay-in ceiling tiles
- All flooring delivered; all flooring supplies now onsite
- All ceiling tiles delivered and now onsite
- Poured HVAC equipment pads
- Installed exhaust fans