Construction Update – 9/11/17 from Ryan Nebel, Construction Superintendent
  • Install cast stone wainscot on top of brick veneer – all elevations.
  • Finish hanging sheetrock and start prepping for paint.
  • Install mechanical duct throughout entire building.
  • Installesprinkler pipe throughout entire building.
  • Continu electrical rough-in throughout building.
  • Hang cement board in bathrooms for tile prep.
  • Blade off grade around building.
  • Clean up site debris.