- Install cast stone wainscot on top of brick veneer – all elevations.
- Finish hanging sheetrock and start prepping for paint.
- Install mechanical duct throughout entire building.
- Installesprinkler pipe throughout entire building.
- Continu electrical rough-in throughout building.
- Hang cement board in bathrooms for tile prep.
- Blade off grade around building.
- Clean up site debris.