Construction Update – 9/25/17 from Ryan Nebel, Construction Superintendent
  • primed painting walls throughout building
  • framed acoustical ceilings throughout building
  • connected permanent power and removing temporary power service
  • pulled construction trailer office from job site
  • set lights and mechanical grills in ceiling
  • hung sheet rock on all hard ceilings
  • completed Hardie plank siding and all window and door trim around building
  • completed hydrotest on sprinkler line